 Dkt No.Date FiledDescription
View20-0900309/03/2020Application of GridLiance West LLC, under the provisions of the Utility Environmental Protection Act, for permits to construct upgrades to the existing Gamebird Substation consisting of the expansion of the substation by approximately 14 acres, a 230 kV transmission line, and associated facilities to be located south of Pahrump in Nye County, Nevada.
View20-0900209/01/2020Joint Application of Nevada Power Company d/b/a NV Energy and Sierra Pacific Power Company d/b/a NV Energy for acceptance of their Joint Energy Supply Plan Update for 2021-2022.
View20-0702607/20/2020Joint Petition of Nevada Power Company d/b/a NV Energy and Sierra Pacific Power Company d/b/a NV Energy requesting deviation from NAC 704.9506 to defer the September 2020 filing of Updated Distributed Resource Plans.
View20-0702507/20/2020Notice by Nevada Power Company d/b/a NV Energy and Sierra Pacific Power Company d/b/a NV Energy, under the provisions of the Utility Environmental Protection Act, of an application to a federal agency for approval to construct the Greenlink West Transmission Line Project consisting of the expansion of the Harry Allen switching station and the Northwest substation, new Amargosa and Esmeralda collector substations, a new Fort Churchill-Northwest 525 kV transmission line, a new Harry Allen-Northwest 525 kV transmission line, and associated facilities to be located in Clark, Nye, Esmeralda, Mineral, and Lyon Counties, Nevada.
View20-0702407/20/2020Notice by Nevada Power Company d/b/a NV Energy and Sierra Pacific Power Company d/b/a NV Energy, under the provisions of the Utility Environmental Protection Act, of an application to a federal agency for approval to construct the Greenlink North Transmission Line Project consisting of the expansion of the Robinson Summit, Comstock Meadows, and Mira Loma substations, a new Fort Churchill substation, a new Fort Churchill-Robinson Summit 525 kV transmission line, a new Comstock Meadows-Fort Churchill 345 kV transmission line, a new Fort Churchill-Mira Loma 345/120 kV transmission line, and associated facilities to be located in White Pine, Eureka, Lander, Churchill, Lyon, Storey, and Washoe Counties, Nevada.
View20-0702307/20/2020Joint Application of Nevada Power Company d/b/a NV Energy and Sierra Pacific Power Company d/b/a NV Energy for approval of the fourth amendment to its 2018 Joint Integrated Resource Plan to update and modify the renewable portion of the Supply-Side Action Plan and the Transmission Action Plan.
View20-0700907/08/2020Application of Sierra Pacific Power Company d/b/a NV Energy, filed under Advice Letter No. 632-E, to revise Electric Tariff No. 1 to modify Net Metering Rider-405 Schedule No. NMR-405 to allow customers residing in condominium buildings to receive electric service under Schedule No. NMR-405.
View20-0700807/08/2020Application of Nevada Power Company d/b/a NV Energy, filed under Advice Letter No. 507, to revise Tariff No. 1-B to modify Net Metering Rider-405 Schedule No. NMR-405 to allow customers residing in condominium buildings to receive electric service under Schedule No. NMR-405.
View20-0700407/01/2020Application of Nevada Power Company d/b/a NV Energy and Sierra Pacific Power Company d/b/a NV Energy for approval of their 2020 Combined Annual Electric Demand Side Management Update Report as it relates to the Action Plan of their 2019-2038 Joint Integrated Resource Plan.
View20-0602006/11/2020Application of Gentry Place Mobile Home Park to withdraw $12,890.78 from the tenant service charge account for reimbursement of expenses incurred to repair and maintain the electrical system.
View20-0600406/01/2020Application of Sierra Pacific Power Company d/b/a NV Energy for approval to adjudicate and establish the cost recovery mechanism for the One Nevada Transmission Line reallocated revenue requirement pursuant to the Order issued in Docket No. 19-05002.
View20-0600306/01/2020Application of Nevada Power Company d/b/a NV Energy for authority to adjust its annual revenue requirement for general rates charged to all classes of electric customers and for relief properly related thereto.
View20-0500405/04/2020Application of Sierra Pacific Power Company d/b/a NV Energy filed under Advice Letter No. 629-E to establish Customer Price Stability Tariff Schedule No. CPST ("the Program") to assist certain qualifying customers during the COVID-19 pandemic and economic downturn, and to address certain customer requests for price stability and potential cost savings in meeting customer-specific business needs and sustainability objectives.
View20-0500305/04/2020Application of Nevada Power Company d/b/a NV Energy filed under Advice Letter No. 504 to establish Customer Price Stability Tariff Schedule No. CPST (the "Program") to assist certain qualifying customers during the COVID-19 pandemic and economic downturn, and to address certain customer requests for price stability and potential cost savings in meeting customer-specific business needs and sustainability objectives.
View20-0203202/28/2020Joint Application of Nevada Power Company d/b/a NV Energy and Sierra Pacific Power Company d/b/a NV Energy for approval of a regulatory asset account to recover costs relating to the development and implementation of their Joint Natural Disaster Protection Plan.
View20-0203102/28/2020Joint Application of Nevada Power Company d/b/a NV Energy and Sierra Pacific Power Company d/b/a NV Energy for approval of their Joint Natural Disaster Protection Plan.
View20-0202502/27/2020Report of Nevada Power Company d/b/a NV Energy and Sierra Pacific Power Company d/b/a NV Energy on the progress of its Action Plan relative to its 2019-2038 Integrated Resource Plan.
View20-0104001/31/2020Joint Application of Nevada Power Company d/b/a NV Energy and Sierra Pacific Power Company d/b/a NV Energy for approval of annual plans for the Solar Energy Systems Incentive Program, the Wind Energy Systems Demonstration Program, the Waterpower Energy Systems Demonstration Program, the Energy Storage and Lower Income components of the Solar Program, and the Electric Vehicle Infrastructure Demonstration Program for Program Year 2020-2021.
View20-0101101/02/2020Filings by Nevada Power Company d/b/a NV Energy and Sierra Pacific Power Company d/b/a NV Energy of its monthly financial statements and quarterly calculations of its earned rate(s) of return and returns on equity for the Nevada jurisdiction pursuant to the Order issued in Docket No. 13-07021.
View20-0100901/02/2020Reports from electric and gas utilities operating in Nevada of transactions and calculations affecting the deferred energy accounts pursuant to NAC 704.195 for calendar year 2020.
View20-0100401/02/2020Annual Reports for calendar year 2019 submitted by Mobile Home Parks operating in Nevada pursuant to NRS 704.960 and NAC 704.987.
View19-1202612/26/2019Rulemaking to consider amending NAC 704.660 and 704.662 to allow the Commission more flexibility in considering cost-of-service studies in advance of Nevada Power Company d/b/a NV Energy’s 2020 general rate case.
View19-1201712/19/2019Application of Nevada Power Company d/b/a NV Energy for approval of an Energy Supply Agreement with Lumen Group LLC.
View19-1000610/07/2019Application of Nevada Power Company d/b/a NV Energy for authority to establish debt issuance authorizations based on a debt ceiling of $3,200.0 million.
View19-0800108/01/2019Filings by Nevada Power Company d/b/a NV Energy and Sierra Pacific Power Company d/b/a NV Energy of its monthly financial statements and quarterly calculations of its earned rate(s) of return and returns on equity for the Nevada jurisdiction pursuant to the Order issued in Docket No. 13-07021.
View19-0701807/25/2019Notice by GridLiance West LLC, under the provisions of the Utility Environmental Protection Act, of an application to a federal agency for approval to construct the Trout Canyon Substation consisting of a new 230 kV substation, appurtenant 230 kV transmission line, and associated facilities to be located approximately 10 miles southwest of Pahrump in Clark County, Nevada.
View19-0603906/24/2019Joint Application of Nevada Power Company d/b/a NV Energy and Sierra Pacific Power Company d/b/a NV Energy for approval of the third amendment to its 2018 Joint Integrated Resource Plan to update and modify the renewable portion of the Supply-Side Action Plan and the Transmission Action Plan.
View19-0600206/03/2019Application of Sierra Pacific Power Company d/b/a NV Energy for authority to adjust its annual revenue requirement for general rates charged to all classes of electric customers and for relief properly related thereto.
View19-0503205/23/2019Monthly reports by Nevada Power Company d/b/a NV Energy and Sierra Pacific Power Company d/b/a NV Energy demonstrating the amount of total incentive funds expended and reserved for all programs funded under NRS 701B.005 pursuant to the Order issued in Docket No. 18-02002.
View19-0500205/01/2019Joint Application of Nevada Power Company d/b/a NV Energy and Sierra Pacific Power Company d/b/a NV Energy for approval to reallocate costs of the One Nevada Transmission Line pursuant to the Order issued in Docket No. 18-06003.
View19-0200202/08/2019Application of Air Liquide Hydrogen Energy U.S. LLC to purchase energy, capacity, and/or ancillary services from a provider of new electric resources.
View19-0100901/02/2019Reports from electric and gas utilities operating in Nevada of transactions and calculations affecting the deferred energy accounts pursuant to NAC 704.195 for calendar year 2019.
View19-0100401/02/2019Annual Reports for calendar year 2018 submitted by Mobile Home Parks operating in Nevada pursuant to NRS 704.960 and NAC 704.987.
View18-1201912/27/2018Application of Las Vegas Resort Holdings, LLC d/b/a Sahara Las Vegas (formerly d/b/a SLS Las Vegas) to purchase energy, capacity, and/or ancillary services from a provider of new electric resources.
View18-1003410/31/2018Amended Application of MSG Las Vegas, LLC to purchase energy, capacity, and/or ancillary services from a provider of new electric resources.
View18-1003010/29/2018Notice by GridLiance West LLC, under the provisions of the Utility Environmental Protection Act, of an application to a federal agency for approval to construct the Carpenter Canyon Substation, consisting of a 230 kV substation and associated facilities, to interconnect an existing 230 kV transmission line with the ARES Nevada LLC Regulation Energy Management project to be located east of Pahrump in Nye County, Nevada.
View18-1002210/19/2018In re: to establish a working group contemplated by Section 15 of the regulations adopted in Docket No. 17-08021 (LCB File No. R022-18).
View18-0901609/26/2018Application of Sierra Pacific Power Company d/b/a NV Energy for authority to establish debt issuance authorizations based on a debt ceiling of $1,600.0 million.
View18-0901509/25/2018Application of Georgia-Pacific Gypsum LLC to purchase energy, capacity, and/or ancillary services from a provider of new electric resources.
View18-0600906/06/2018Application of Fulcrum Sierra BioFuels, LLC to purchase energy, capacity, and/or ancillary services from a provider of new electric resources.
View18-0600306/01/2018Joint Application of Nevada Power Company d/b/a NV Energy and Sierra Pacific Power Company d/b/a NV Energy for approval of their 2019-2038 Triennial Integrated Resource Plan and 2019-2021 Energy Supply Plan.
View18-0100401/02/2018Annual Reports for calendar year 2017 submitted by Mobile Home Parks operating in Nevada pursuant to NRS 704.960 and NAC 704.987.
View17-1201812/27/2017Notice by Hydrostor A-CAES USA Inc., under the provisions of the Utility Environmental Protection Act, of an application to a federal agency for approval to construct an advanced compressed air energy storage facility to be located approximately 10 miles outside of Ely in White Pine County, Nevada.
View17-0701607/14/2017Notice by Southern California Public Power Authority, under the provisions of the Utility Environmental Protection Act, of an application to a federal agency for approval to construct the Apex Transmission Line consisting of approximately 10 to 14 miles of 500 kV transmission line and associated facilities to be located in Clark County, Nevada.
View17-0600406/05/2017Application of Nevada Power Company d/b/a NV Energy for approval of new and revised depreciation and amortization rates for its electric and common accounts.
View17-0600306/05/2017Application of Nevada Power Company d/b/a NV Energy for authority to adjust its annual revenue requirement for general rates charged to all classes of electric customers and for relief properly related thereto.
View16-0902309/30/2016Application of Switch Ltd. to purchase energy, capacity, and/or ancillary services from a provider of new electric resources.
View16-0700407/01/2016Application of Nevada Power Company d/b/a NV Energy for authority to restate $1,277.5 million of existing long term debt authority and issue new refinancing authority of $1,323.2 million.
View16-0601706/14/2016Notice by TransCanyon, LLC, under the provisions of the Utility Environmental Protection Act, of an application to a federal agency for approval to construct approximately 214 miles of 500 kV transmission line connecting the existing Thirty Mile/Robinson Summit and Mona/Clover substations and associated facilities, portions of which will be located in White Pine County, Nevada
View14-0901509/22/2014Petition of the Regulatory Operations Staff for an Order directing Nevada Power Company d/b/a NV Energy and Sierra Pacific Power Company d/b/a NV Energy to file requested information with the Commission regarding the advanced metering infrastructure.
View12-0802308/22/2012Application of Moapa Solar, LLC, under the provisions of the Utility Environmental Protection Act, for a permit to construct a 7.5 mile 230 kV overhead transmission line to the Harry Allen Substation and a 1.5 mile 500 kV overhead transmission line to connect a solar facility located on the Moapa River Indian Reservation to the existing Crystal Valley and Harry Allen Substations located in Clark County, Nevada.
View11-0500205/06/2011Application of Nevada Power Company d/b/a NV Energy and Sierra Pacific Power Company d/b/a NV Energy, under the provisions of the Utility Environmental Protection Act, for a permit to construct approximately 138 miles of new overhead 230 kV, 345 kV, and/or 500 kV electric transmission lines and associated facilities to be located in Nye and Clark Counties, Nevada.
View09-1100511/04/2009Application of TransWest Express LLC for authority under the provisions of the Utility Environmental Protection Act for a permit to construct the TransWest Express Transmission Project consisting of a 600 kV DC transmission line running from central Wyoming to southern Nevada and associated facilities.